Client: Satterley Property Group
Project Design:
Spiire
Contract Sum: $2.3M
ABOUT THE PROJECT
Arcadia Officer South Road Culverts
In order to facilitate the flow between NH02 and NH03 waterways, a triple cell culvert system was constructed, which also allowed for the future upgrade of Officer South Road into a major Arterial Road. The 50m of 3m wide by 1.5m high triple cell culvert system was designed to VicRoads standards, including wing walls 600mm thick.
WORKS
- 50m of 3m wide by 1.5m high triple cell culvert system
- High Voltage Electrical Relocation
- High Pressure Gas Main Relocation
- 600mm thick headwall and wingwalls
- Construction of impact barrier
KEY ASPECTS
- Construction of culverts in accordance to VicRoads specification
- Realignment of HV Main and High Pressure Gas Main
- Staged construction to facilitate asset relocations
- Working below groundwater table
- Working between two active waterways