PROJECT INFO

Client: Mornington Peninsula Shire Council

Project Design:

GHD

Contract Sum: $0.3M

View PDF

ABOUT THE PROJECT

Beleura Cliff Path Landslip Rehabilitation

The Beleura Cliff Path is an iconic scenic walk that leads from Caraar Creek Lane  down to the north end of Mills Beach, Mornington.  It’s an historic  path, cut with pick and shovel between 1916 and 1923 for the public to use, and is famous for its serene views of the cliffs, rocks and sea.

Poor stormwater management had caused a major landslip and subsequent closure of the path for safety reasons. Entracon was contracted to stabilise the landslip, construct and install sufficient stormwater drainage and reconstruct the path and subsequent landscaping.

 

WORKS

  • Cliff stabilisation,
  • Earthworks
  • Drainage
  • Path construction
  • Landscaping

 

KEY ASPECTS

  • Poor site access
  • Working at heights
  • Sand bag installation
  • Pedestrian Management

 