PROJECT INFO
Client: Mornington Peninsula Shire Council
Project Design:
GHD
Contract Sum: $0.3M
ABOUT THE PROJECT
Beleura Cliff Path Landslip Rehabilitation
The Beleura Cliff Path is an iconic scenic walk that leads from Caraar Creek Lane down to the north end of Mills Beach, Mornington. It’s an historic path, cut with pick and shovel between 1916 and 1923 for the public to use, and is famous for its serene views of the cliffs, rocks and sea.
Poor stormwater management had caused a major landslip and subsequent closure of the path for safety reasons. Entracon was contracted to stabilise the landslip, construct and install sufficient stormwater drainage and reconstruct the path and subsequent landscaping.
WORKS
- Cliff stabilisation,
- Earthworks
- Drainage
- Path construction
- Landscaping
KEY ASPECTS
- Poor site access
- Working at heights
- Sand bag installation
- Pedestrian Management