ABOUT THE PROJECT
Lyndhurst North Drainage Scheme Outfall Drain Contract
Stage 1 & 2 Works include:
- Supply and install box culverts under Taylors Road
- Supply and install culverts in Stages across SITA waste management access road.
- Open channel works.
- Rock beaching of works
- Install farm crossings
- Install, replace irrigation piping
Site Issues :
- SITA access
- Safely of public
- Flood Management
- Disposal of haza rdou s & other types of materials
- Market garden relations
- Environmental iss ues