PROJECT INFO

Client: Parks Victoria

Design: SMEC Aust

 

Contract Sum

$3.0 M

View PDF

ABOUT THE PROJECT

Lysterfield Lake Remediation Works

Site Issues:

  • Wet weather
  • 3 mths delay due to VicR oad site entry requirements
  • Ground water
  • Environmenta l co ntrols
  • Fill testing requir ement for patho­ gens
  • Confined space work

Works Undertaken:

  • Importatio n of 90,000 1cm of clay fill
  • Placement of approx $1,000,000 of quarry products
  • Sa nd blas ting & paintin g of existing outlet pipe under confined space cond it ions
  • Outlet pit construction
  • Co nst ruction of internal roads & drainage
  • Native seeding @ $250/kg.