PROJECT INFO

Client: Central Highlands Water

Project Design:

MWH

Contract Sum:

$3M

View PDF

ABOUT THE PROJECT

Wilson Reservoir

Works Include:

• Chimney Filter / Drains with Weighting Buttress.
• Filter Cutoff trench
• Outlet works, including Concrete encasement, brickwork and discharge channel
• Cured in Place Pipe (CIPP)
• New auxiliary spillway including Cutoff and Riprap
• Crest capping materials and Piezometer Extensions
• Establishment and monitoring or temporary deformation monitoring survey points
• Salvage of existing outlet works structure brickwork
• Construction of embankment swale drain

Key Aspects:

• High Bushfire Risk
• Protection of Heritage Buildings
• Maintaining water level in reser­voir while under construction
• High Rainfall Risk