PROJECT INFO

Client: Barwon Water

 

Project Design:

Kellogg, Brown &Root P/L

 

Contract Sum: $ 5.6 M

View PDF

ABOUT THE PROJECT

Wurdee Buloc Water Filtration Plant Upgrade, VIC.

Works Included:

  • Construction of a complete backwash pump station.
  • Installation of 900 to 1750mm diameter welded MSCL pipe.
  • Several critical shutdowns of the water treatment plant.
  • Low rise construction.
  • 1500m2 of asphalt pavement works.
  • Construction of S/S backwash system.
  • Significant electrical, instrumentation and control works.

Entracon would like to thank Barwon Water, KBR and the entracon team for the collaborative effort in which this project was undertaken. It was a pleasure to work together on the project and we look forward to future cooperative endeavours.

Gallery