PROJECT INFO

Client: Client: Vic Roads for Akron Roads

Client Representative:

Akron Roads
Robert Davies — Project Manager
Project Manager—Rob Davies
Designers — Hyder Consulting

View PDF

ABOUT THE PROJECT

Thompsons Road, Bridge Works

Works Included:

  • Modification of existing abutments Piling
  • Casting of new crossheads & abutments
  • Installation of pre-stressed T-beams
  • Pouring of insitu cover slab
  • Installation of traffic barriers
  • Melbourne Water Open Drain modifications

Site Issues:

  • Heavy Vehicle Traffic
  • Stream Flows
  • Overhead power lines
  • 12 hour construction period
  • Vic Road’s re-design delays