PROJECT INFO

Client: Stonnington City Council

Project Design: Greg Schofield & Associates Pty Ltd

Contract Sum:  $1.2M

ABOUT THE PROJECT

Sir Robert Menzies Reserve Retaining Wall - Malvern East

Entracon was engaged by Stonnington City Council for the replacement of the retaining wall at the southern end of Sir Robert Menzies Reserve in Malvern East.
The new curved precast concrete crib wall replaced the existing structure which had been rapidly deteriorating, providing important safety works for the park patrons and local residents whose properties were directly affected by the weakening wall.
All works were completed in house with Entracon’s vast and specialised staff and machines.

WORKS

  • 42 bored piles (600mm and 900mm)
  • 130m of multi-angled precast concrete crib wall construction
  • Drainage
  • Landscaping and turfing

KEY ASPECTS

  • Working on slopes
  • Management of contaminated material
  • Deep piling
  • Construction within a sensitive suburban area